With just ten months remaining in the construction of U.S. Bank Stadium, here are a few quick updates on construction progress and expectations moving forward:Follow the Staircase
The east side of the stadium is beginning to look like the finished product, with all glazing, paneling, signage, stairs and entry work complete. The finished concrete staircase, located directly above the loading dock, gives stadium users their first glimpse at entering the facility from the east side. To alleviate heavy loads of soil and to maximize the load placed on the concrete structure, Mortenson Construction used 5,000 cubic yards of geofoam, a stable, lightweight, waterproof fill that is 1-2% of the weight…