Change orders for Falcons stadium reach $208M

The Falcons made another $9.1 million worth of changes to the new Mercedes-Benz Stadium last month, according to a report prepared by a state agency.

The latest project status report by the Georgia World Congress Center Authority said the Falcons organization had “issued change orders” to general contractor Holder Hunt Russell Moody “in the cumulative amount of $208.6 million for various scope changes” through June.

That’s up from the previously reported $199.5 million in change orders through May.