On Feb. 13, 2017 the Harper Corporation and Garney Construction Company, Inc. were provided with the Notice to Proceed on the Boone Water Line, Water Treatment Plant, Intake and Booster Pump Station Project. The following is a project update and notice of any upcoming road closures. There are currently 246 days remaining in the project contracts.

The Harper Corporation continues to complete items at the water treatment plant, the water intake site and at the Brownwood Road booster pump station. Dewatering systems remain in place and in operation at the intake site.