The U.S. Soccer Federation and FC Dallas have released details of an updated construction timeline for the National Soccer Hall of Fame at Toyota Stadium. From that we also have some new renderings that show how the street level view will be from outside the stadium and the new locker rooms.

National Soccer Hall of Fame Estimated Construction Timeline*

  • Winter 2017 – South end zone seating in place
  • Summer 2018 – Locker rooms, Lamar Hunt U.S Open Cup Hall of Fame club and terrace, roof structure, team store, box office and press conference areas completed
  • Winter 2018 – Concourse level Hall of Fame Club and Museum completed

*all estimated completion dates are subject to change

The new roof looks very nice compared to previous renderings that we’ve seen.